USCG approves Brighline’s request to temporarily close the St. Lucie River navigation channel
St. Lucie River Railroad Bridge Work Schedule
• Overnight closures: 8 p.m. to 6 a.m., SUNDAY, APRIL, 16 to THURSDAY, APRIL 27. Drawbridge to remain in the down position OVERNIGHT; NO BOAT PASSAGE. Navigation channel open daily from 6 a.m. to 8 p.m. (subject to normal train traffic). Drawbridge returns to normal operations 6 a.m., Friday, April 28.
• Full Closure – 6 a.m., MONDAY, MAY 1 to 6 a.m., MONDAY, MAY 22. Navigation channel FULL CLOSURE (drawbridge to remain in the down position, no boat passage). Brightline crews will work 24/7.
• Overnight closures: 8 p.m. to 6 a.m., MONDAY, MAY 22 to SUNDAY, MAY 28. Drawbridge to remain in the down position OVERNIGHT, no boat passage. Navigation channel open daily from 6 a.m. to 8 p.m. (subject to normal train traffic). Drawbridge returns to normal operations 6 a.m., Monday, May 29.