FDOT Treasure Coast Traffic Report 3/26-4/2 2021

FDOT Treasure Coast Traffic Report 3/26-4/2 2021

 

MARTIN, ST. LUCIE & INDIAN RIVER COUNTIES, Fla. – Construction, maintenance and permit-related lane closures on state highways in Martin, St. Lucie and Indian River counties are expected during March 26 through April 2, 2021. Weather permitting, work will be done at the following locations throughout the Treasure Coast.  For updated lane closure information, please refer to www.d4fdot.com. Follow us on Twitter and Instagram @ MyFDOT_SEFL and on Facebook @MyFDOTSEFL. Please note, any full road, ramp or bridge closures have been highlighted below

SAFETY MESSAGE

March is Florida Bicycle Month

 

Did you know that 60% of Florida’s population lives within one mile of bicycle facilities? Everyone has the expectation, and right, to arrive at their destination safely no matter what mode of transportation they use.

  • When driving, stay alert and watch for pedestrians and bicyclists especially at night.
  • When riding at night, always use a headlight, taillight, and reflectors. Wearing light-colored or reflective clothing can also make you more visible during dark or dusk hours.

See attached bike signs and signals brochure and visit www.fdot.gov/agencyresources/bicyclesafety for more information.

 

 

CONSTRUCTION PROJECTS

MARTIN COUNTY

 

  1. Kanner Highway / State Road 76, from south of Pratt Whitney Road (County Road 711) to SW Jack James Drive

Description: Kanner Highway is being widened from south of Pratt Whitney Road to SW Jack James Drive. Work on this 1.94-mile project includes: reconstructing Kanner Highway from CR 711 to Locks Road from a two-lane undivided highway to a four-lane divided highway with a raised median and curb & gutter; adding seven-foot-wide bicycle lanes from CR 711 to Locks Road; adding a 12-foot-wide shared use path on the east side of Kanner Highway from CR 711 to Locks Road; adding a six-foot-wide sidewalk on the west side of Kanner Highway from CR 711 to Locks Road; installing drainage features that will improve drainage; and resurfacing Kanner Highway from Locks Road to SW Jack James Drive. Access points and turn lanes will be provided throughout the corridor at the following locations: there will be turn lanes at the two signalized intersections CR 711 and Locks Road; full median openings will be at Mary Drive, Tropical Avenue, and SW Old Royal Drive; and a left-turn-only median opening will be located at Beverly Terrace.

Cost/Completion: $12.9 million. Completion is expected in summer 2021.

Traffic Impact:

  • The speed limit on Kanner Highway from south of Pratt Whitney Road to SW Jack James Drive has been temporarily reduced from 50 MPH to 45 MPH. This speed limit reduction will be in place through the end of the project.
  • One lane in either direction of Kanner Highway from Pratt Whitney Road to SW Jack James Drive will be closed intermittently Saturday and Monday through Friday from 7 a.m. to 7 p.m. for roadway work.
  • One lane in either direction of Pratt Whitney Road at the Kanner Highway intersection will be closed Saturday and Monday through Friday from 7 a.m. to 7 p.m. for roadway work.
  • The sidewalk on the west side of Kanner Highway is closed. Pedestrians should use the newly constructed shared use path on the east side of Kanner Highway. Please note, due to current roadway conditions the shared use path terminates prior to Locks Road and Pratt Whitney Road/SW96th Street for pedestrian safety. For more information, please contact Community Outreach Specialist Kathleen Dempsey at 772-359-5118.

 

  1. U.S. 1 Shoulder Widening and Resurfacing Project, from South of SE Heritage Boulevard to North of SE Salerno Road

Description: U.S. 1 is undergoing a shoulder widening and resurfacing project from south of SE Heritage Boulevard to north of SE Salerno Road. The improvements include: milling and resurfacing of all travel lanes, turn lanes, and shoulders; widening the shoulders to accommodate 7-foot buffered bicycle lanes; addressing pavement failures at Cove Road and Salerno Road; upgrading sidewalk and pedestrian ramps to meet American with Disabilities Act (ADA) standards; upgrading signing and pavement markings; installing new pedestrian countdown signal heads at multiple signalized intersections; upgrading traffic controller cabinets at all signalized intersections; and installing lighting improvements at Salerno Road and Cove Road intersections.

Cost/Completion: $8.4 million. Completion is expected in spring 2021.

Traffic Impact:

  • One lane in either direction of U.S. 1 from Heritage Boulevard to Salerno Road will be closed Monday through Friday from 8 a.m. to 5 p.m. for striping. This lane closure may also occur Sunday through Thursday night from 6 p.m. to 6 a.m. For more information, please contact Community Outreach Specialist Kathleen Dempsey at 772-359-5118.

County Work Not Project Related:

  • Work is occurring to mill and overlay of the westbound right turn lane on SE Cove Road at the intersection of SE Cove Road and U.S. 1. This work will necessitate closing the turn lane and the adjacent sidewalk on SE Cove Road from SE Finley Avenue to U.S. 1, weekdays from 7 a.m. to 4 p.m. The work is anticipated to be complete by April 19, 2021. Motorists, pedestrians, and cyclists are encouraged to follow detours, exercise caution, and expect minor delays. For more information, please contact Angelica Bassetti with Martin County Public Works at 772-288-5466.

 

  1. I-95 Lighting and Roadway Improvements Project from South of the State Road 706 / Indiantown Road Interchange to the County Road 708 / SE Bridge Road Interchange

Description: This 11.59-mile I-95 improvements project started September 9, 2020 in Jupiter and Hobe Sound. Work includes installing new roadway lighting with LED luminaires, replacing the high mast lighting system with a conventional LED roadway lighting system, extending the northbound I-95 merge lane just north of Indiantown Road, extending the deceleration distances for the I-95 northbound to westbound Indiantown Road exit ramp and the I-95 southbound to eastbound Indiantown Road exit ramp, and installing wrong way vehicle detection systems at the Indiantown Road and SE Bridge Road I-95 interchanges and new advanced warning signage.

Cost/Completion: $12.3 million. Completion is expected in spring 2022.

Traffic Impact:

  • The shoulder in both directions of I-95 will be intermittently closed Monday through Friday from 6:30 a.m. to 6 p.m. through Aug. 2021 for temporary asphalt placement, landscaping relocation efforts, and conduit and light pole foundation installations.
  • One lane in either direction of I-95 at the Indiantown Road interchange may be closed Sunday through Thursday night from 10 p.m. to 6 a.m. to maintain the barrier wall installed for the traffic diversion.
  • One lane in each direction of Indiantown Road from the Turnpike entrance/exit to Island Way will be closed Monday through Friday from 10 a.m. to 3 p.m. to install light pole foundations. For more information, please contact Community Outreach Specialist Kathleen Dempsey at 772-359-5118.

 

  1. US 1 Improvements Project from North of Britt Road to South of Jensen Beach Boulevard/State Road 732

Description: On March 4, 2020, construction started on US 1 from north of Britt Road to south of Jensen Beach Boulevard. The purpose of this project is to provide a fourth continuous northbound thru/shared right-turn lane between Britt Road and Jensen Beach Boulevard. Work at the US 1/SR 5 and Treasure Coast Square Mall south entrance intersection includes: reconstructing curb ramp and sidewalk at the northeast corner; widening the roadway at the northeast corner; and removing the existing double mast arm signal pole at the northeast corner, and replacing it with new signal mast arms at the northeast and southeast corners. Additional work on this project includes restriping northbound US 1 lanes to provide a continuous thru/shared right-turn lane and bike lane, and milling and resurfacing the existing two outside northbound lanes to accommodate restriping.

Cost/Completion: $547.644. Completion is expected in summer 2021.

Traffic Impact:

  • The outside northbound U.S. 1 turn lane just south of the south mall entrance will be closed Monday through Friday from 8 a.m. to 6 p.m. to facilitate mast arm installation. Motorists can still make a right into the shopping plaza using the outside northbound U.S. 1 through lane.
  • The outside westbound lane coming from the shopping plaza will be closed Monday through Friday from 8 a.m. to 6 p.m. to facilitate mast arm installation. Motorists can still make a right onto U.S. 1 or head straight towards the Treasure Coast Square Mall using the inside westbound lane.
  • The sidewalk along the east side of U.S. 1 at the south mall entrance intersection is closed around the clock through Apr. 2021. Pedestrians should detour to the nearest signalized intersections. For more information, please contact Community Outreach Specialist Kathleen Dempsey at 772-359-5118.

 

  1. Martin Downs Boulevard at Matheson Avenue in Palm City

Traffic Impact:

  • One westbound lane of Martin Downs Boulevard will be closed Monday through Friday from 9 a.m. to 3:30 p.m. through Apr. 16 for utility work. For more information, please contact Daniel Moura at 561-418-0598.

 

  1. Kanner Highway just South of South River Road in Stuart

Traffic Impact:

  • One southbound lane of Kanner Highway will be closed Monday through Friday from 9 a.m. to 3:30 p.m. through Apr. 16 for utility work. For more information, please contact Daniel Moura at 561-418-0598.

 

  1. U.S. 1 from Wright Boulevard to Britt Road in Stuart

Traffic Impact:

  • One northbound lane of U.S. 1 from Wright Boulevard to Britt Road will be closed Monday through Friday from 9 a.m. to 4 p.m. for utility work. For more information, please contact Gus Sikaffy at 954-995-2760.
  • One northbound lane of U.S. 1 from Wright Boulevard to Baker Road will be closed Monday through Friday from 9 a.m. until 4 p.m. through Apr. 30 for median work with sod, concrete pouring, irrigation installation and landscaping. For more information, please contact Michael Forman at 772-794-4100.

 

  1. State Road A1A from NE Rose Walk Terrace to NE Causeway Boulevard in Stuart & Jensen Beach

Traffic Impact:

  • One lane in either direction of State Road A1A will be closed Monday through Friday from 9 a.m. to 4 p.m. for utility work. Two-way traffic will be maintained by a flag crew. For more information, please contact Gus Sikaffy at 954-995-2760.

 

  1. U.S. 1 from Goldenrod Road to Westmoreland Boulevard in Jensen Beach

Traffic Impact:

  • Two northbound lanes of U.S. 1 will be closed Sunday through Thursday night from 9 p.m. to 6 a.m. for utility work. For more information, please contact Gus Sikaffy at 954-995-2760.

 

  1. Jensen Beach Boulevard from Fowler Avenue to Green River Parkway in Jensen Beach

Traffic Impact:

  • One lane in each direction of Jensen Beach Boulevard will be closed Monday through Friday from 9 a.m. to 4 p.m. for utility work. For more information, please contact Gus Sikaffy at 954-995-2760.

 

  1. U.S. 1 from Dharlys Street to Constitution Boulevard in Hobe Sound

Traffic Impact:

  • One northbound lane of U.S. 1 will be closed Monday through Friday from 9 a.m. to 4 p.m. for utility work. For more information, please contact Gus Sikaffy at 954-995-2760.

 

  1. U.S. 1 from Bridge Road to Algozzini Place in Hobe Sound

Traffic Impact:

  • One northbound lane of U.S. 1 will be closed Monday through Friday from 9 a.m. to 4 p.m. for utility work. For more information, please contact Gus Sikaffy at 954-995-2760.

 

  1. I-95 Approximately Three Miles North of High Meadow Avenue / Exit 102

Traffic Impact:

  • Advance Notice: One northbound lane of I-95 will be closed Sunday night, Apr. 4 through Tuesday night, Apr. 6 from 9 p.m. to 5 a.m. for bridge work. For more information, please contact Diego Marentes at 772-215-9338.

 

  1. LUCIE COUNTY

 

  1. Midway Road Widening Project, from S. 25th Street to U.S. 1

Description: This 1.8-mile project includes: reconstructing the existing two-lane Midway Road to a four-lane, divided highway with a raised median; installing a new signal at Sunrise Boulevard; constructing a new bridge over the North Fork St. Lucie River; constructing a 6-foot sidewalk on the north side and a 12-foot multi-purpose trail on the south side Midway Road; constructing 4-foot bike lanes on both sides of the roadway; reconstruction of S. 25th Street approximately 1000’ to the south & north of Midway Road; reconstruction of Sunrise Boulevard from W. 1st Street to Charlotta Street; reconstruction of Oleander Avenue from W. 2nd Street to Merritt’s Ditch; drainage improvements, including constructing 6 retention ponds at 5 locations; and signage, signalization, and lighting improvements.

Cost/Completion: $26.8 million. Completion is expected in fall 2021.

Traffic Impact:

  • One lane in either direction of Midway Road between 25th Street and U.S. 1 may be closed Monday through Friday except from 6:30 a.m. to 9 a.m. & 4 p.m. to 8:30 p.m. for drainage activities, signalization, bridge work, and embankment/excavation. Two-way traffic will be maintained with a flag crew.
  • One lane in either direction of Oleander Avenue between West 1st Street and just north of Midway Road by Merritt’s Ditch may be closed Monday through Friday except from 7 a.m. to 9 a.m. & 4 p.m. to 6 p.m. Two-way traffic will be maintained with a flag crew.
  • One lane in either direction of Sunrise Boulevard between West 1st Street and Augusta Street may be closed Monday through Friday except from 7 a.m. to 9 a.m. & 4 p.m. to 6 p.m. Two-way traffic will be maintained with a flag crew.
  • One lane in each direction of 25th Street from 1,200’ north to 500’ south of Midway Road will have daytime and nighttime lane Monday through Friday except for between the hours of 3 p.m. and 7 p.m. for paving.
  • One lane in either direction of Melville Road just south of Midway Road may be closed Monday through Friday except from 7 a.m. to 9 a.m. & 4 p.m. to 6 p.m. A flag crew will maintain two-way traffic.
  • One lane in either direction of U.S. 1 at Midway Road may be closed Monday through Friday except from 7 a.m. to 9 a.m. & 4 p.m. to 6 p.m.
  • Northbound and southbound traffic on Oleander Avenue from 2nd Street to Merritt’s Ditch is shifted to the west on the newly constructed roadway to facilitate roadway construction to the east.
  • Northbound and southbound traffic on Sunrise Boulevard from 1st Street to Charlotta Street is shifted to the west on the newly constructed roadway to facilitate roadway construction to the east.

 

  1. Kings Highway Widening Project, from South of State Road 70 to North of the I-95 Overpass

Description: Kings Highway / State Road 713 is being widened from south of State Road 70 to north of the I-95 overpass in the City of Ft. Pierce and unincorporated St. Lucie County. The improvements on this 3.417-mile project include: reconstructing the existing two-lane undivided Kings Highway with a newly constructed four‐lane divided roadway, relocating Canal No. 40 and Canal No. 32E to accommodate widening to the west, realigning Kings Highway at the intersection with Okeechobee Road which will improve the existing connection with the Turnpike, replacing existing culverts/swales and installing a closed drainage system and retention ponds, installing a new highway lighting system, and upgrading signalization with vehicle detection devices and ITS cameras.

Cost/Completion: $45.2 million. Completion is expected in fall 2022.

Traffic Impact:

  • The speed limit on Kings Highway from south of Okeechobee Road / State Road 70 to north of the I-95 overpass has been temporarily reduced from 50 MPH to 40 MPH. This speed limit reduction will be in place through the end of the project.
  • One lane in either direction of Kings Highway may be intermittently closed Monday through Friday from 9 a.m. to 4 p.m. through fall 2022 for roadway work. Two-way traffic will be maintained by a flag crew. During this time, intermittent side street closures may occur, maintaining two-way traffic at all times.
  • Southbound Kings Highway just north of Okeechobee Road is shifted to the east through spring 2021 to facilitate roadway reconstruction. During this time, the southbound to eastbound turning lanes is reduced to one lane.
  • Southbound and northbound Kings Highway at the Orange Avenue intersection is reduced to one lane in each direction through summer 2021, temporarily removing the designated turning lanes, to facilitate roadway reconstruction.
  • Eastbound Orange Avenue just west of Kings Highway is reduced to one through lane through summer 2021 to facilitate roadway reconstruction.
  • Northbound and southbound traffic on Kings Highway from just north of Crossroads Parkway to south of Orange Avenue is shifted to the east on the newly constructed road to facilitate reconstruction of Kings Highway. Please note, westbound traffic on Graham Road will not need to pull forward as far when coming to a complete stop before turning north or south onto Kings Highway. For more information, please contact Community Outreach Specialist Kathleen Dempsey at 772-359-5118.

 

  1. “Jobs Express Terminal” Gatlin Boulevard Park and Ride Lot Project

Description: The “Jobs Express Terminal” Gatlin Boulevard park and ride lot project started August 23, 2020. The future location of this park and ride lot is just east of the I-95 interchange, between Brescia Street and Edgarce Street. The purpose of the project is to support regional commuter trips to and from the greater St. Lucie County area by constructing a park and ride lot with the capacity to hold 162 vehicles and installing bus shelters for drop-off or pick-up.

Cost/Completion: $2 million. Completion is expected in spring 2021.

Traffic Impact:

  • One eastbound lane of Gatlin Boulevard from Brescia Street and Edgarce Street will be closed Monday through Friday from 9 a.m. to 4 p.m. through Apr. 2021 for construction of a permanent driveway.
  • One northbound lane of Brescia Street just south of Gatlin Boulevard may be closed Sunday through Thursday night from 11 p.m. to 6 a.m. through Apr. 2021 for driveway turnout construction. During this time, pedestrian traffic may be detoured to the other side of Brescia Street.
  • The westbound lane of Hayworth Avenue between The Home Depot and Edgarce Street may be closed Monday through Friday from 9 a.m. to 4 p.m. through Apr. 2021 for driveway turnout construction. Two-way traffic will be maintained by a flag crew. For more information, please contact Community Outreach Specialist Kathleen Dempsey at 772-359-5118.

 

  1. US 1/State Road 5 and State Road 70 Advanced Transportation Management Center (ATMS) Improvements Design-Build Project

Description: Construction on the U.S. 1/State Road (SR) 5 and SR 70 (Okeechobee Road/Virginia Avenue) ATMS improvements design-build project started September 29, 2020. The improvements to this project include installing closed circuit television (CCTV) cameras and Bluetooth detection devices that will transmit to the Traffic Management Center at the following locations: U.S. 1 from Savanna Club Boulevard to Kings Highway/SR 713, and SR 70 from Kings Highway/SR 713 to U.S. 1.

Cost/Completion: $6.4 million. Completion is expected in fall 2021.

Traffic Impact:

  • The northbound and southbound shoulders of U.S. 1 from North 3rd Street to Kings Highway will be intermittently closed Monday through Friday from 7 a.m. to 5 p.m. through Apr. 30 for utility work.
  • One northbound lane of U.S. 1 from Orange Avenue to Causeway Drive will be intermittently closed Monday through Friday from 9 a.m. to 4 p.m. through Apr. 30 for conduit and pull box installation. During this time, intermittent sidewalk closures will occur, detouring pedestrians to the nearest signalized intersection.
  • One southbound lane of U.S. 1 from Avenue C to Avenue M will be intermittently closed Monday through Friday from 9 a.m. to 4 p.m. through Apr. 30 for conduit and pull box installation. During this time, intermittent sidewalk closures will occur, detouring pedestrians to the nearest signalized intersection.
  • The southbound shoulder of U.S. 1 from Savanna Club Boulevard to Rio Mar Drive will be closed intermittently Monday through Friday from 9 a.m. to 4 p.m. through Apr. 30 for conduit and pull box installation. During this time, intermittent sidewalk closures will occur, detouring pedestrians to the nearest signalized intersection.
  • One northbound lane of U.S. 1 from Rio Mar Drive to Orange Avenue will be intermittently closed Monday through Friday from 9 a.m. to 4 p.m. through Apr. 30 for conduit and pull box installation. During this time, intermittent northbound turn lane and sidewalk closures will occur. Pedestrians will be detoured to the nearest signalized intersection.
  • One eastbound lane of State Road 70 from South 41st Street to U.S. 1 will be closed Monday through Friday from 9 a.m. to 4 p.m. through Apr. 30 for conduit and pull box installation.
  • One lane in each direction of State Road 70 from Kings Highway to South 41st Street will be closed Monday through Friday from 9 a.m. to 4 p.m. through Apr. 30 for conduit and pull box installation. For more information, please contact Community Outreach Specialist Kathleen Dempsey at 772-359-5118.

 

  1. U.S. 1/State Road (SR) 5 Improvement Projects

Description: Construction on the U.S. 1 improvement projects from south of Port St. Lucie Boulevard/SR 716 to Rio Mar Drive and at Virginia Avenue/SR 70 started November 19, 2020. The improvements under this contract consist of milling and resurfacing the existing roadway and restriping to provide 6‐foot buffered bicycle lanes on U.S. 1 from south of SR 716 to Rio Mar Drive, and widening the existing roadway in the NW corner of the U.S. 1 and SR 70 intersection to accommodate a southbound right-turn lane.

Cost/Completion: $7,223,963. Completion is expected in spring 2022.

Traffic Impact:

  • One lane in each direction of U.S. 1 from Port St. Lucie Boulevard to Rio Mar Drive will be intermittently closed Monday through Friday from 9 a.m. to 4 p.m. for sidewalk repair work. During this time, sections of the sidewalk will be closed. Detour signage will be in place, directing pedestrians to the nearest signalized intersection. For more information, please contact Community Outreach Specialist Kathleen Dempsey at 772-359-5118.

Utility Work Not Construction Related:

  • One northbound lane of U.S. 1 from Village Drive to Veterans Memorial Parkway will be closed Monday through Friday from 9 a.m. to 4 p.m. for utility work. For more information, please contact Gus Sikaffy at 954-995-2760.

 

  1. Port St. Lucie Boulevard from Floresta Drive to Stargrass Street in Port St. Lucie

Traffic Impact:

  • One eastbound lane of Port St. Lucie Boulevard will be closed Wednesday through Friday from 9 a.m. to 4 p.m. for mast arm installation work. For more information, please contact Adam Schmidt at 772-220-2728.

 

  1. Port St. Lucie Boulevard at Delano Road in Port St. Lucie

Traffic Impact:

  • One lane in each direction of Port St. Lucie Boulevard will be closed Monday through Friday from 9 a.m. to 3:30 p.m. through Apr. 21 for signal installation work. For more information, please contact Jake Ridinger at 772-201-1621.

 

  1. State Road A1A from Jackson Way to Regal Road in Ft. Pierce

Traffic Impact:

  • The northbound lane of State Road A1A will be closed Monday through Friday from 9 a.m. to 4 p.m. for utility work. Two-way traffic will be maintained by a flag crew. For more information, please contact Gus Sikaffy at 954-995-2760.

 

  1. 25th Street from Edwards Road to Cortez Boulevard in Ft. Pierce

Traffic Impact:

  • One southbound lane of 25th Street will be closed Monday through Friday from 9 a.m. to 4 p.m. for utility work. For more information, please contact Gus Sikaffy at 954-995-2760.

 

  1. Virginia Avenue from 35th Street to 39th Street in Ft. Pierce

Traffic Impact:

  • One westbound lane of Virginia Avenue will be closed Monday from 9 a.m. to 4 p.m. to construct a business entrance. For more information, please contact Brandon Paul at 321-577-4925.

 

  1. Indrio Road and Kings Highway Intersection in Ft. Pierce

Traffic Impact:

  • One westbound lane of Indrio Road at the Kings Highway intersection will be closed Monday through Friday from 9 a.m. to 4 p.m. to install a business turn lane. During this time, there will be turning lane closures on Kings Highway. For more information, please contact Ron Buchmeyer at 772-201-5683.

 

  1. State Road 70 from McNeil Avenue to Oleander Avenue in Ft. Pierce

Traffic Impact:

  • One lane in either direction of State Road 70 will undergo a rolling lane closure Monday through Thursday night from 9 p.m. to 4 a.m. through Apr. 6 for sign installation. For more information, please contact John Whitford at 772-349-8029.

 

  1. Southbound Florida’s Turnpike/SR 91 Exit Ramp to Okeechobee Road/SR 70 (Exit 152)

Traffic Impact:

  • Full Closure: Southbound Florida’s Turnpike/SR 91 exit ramp to Okeechobee Road/SR 70 (Exit 152) will undergo an overnight full ramp closure, 10 p.m. Sunday, March 28, to 6 a.m. Monday, March 29, and overnight full ramp closures, 9 p.m. to 6 a.m., Monday, March 29, and nightly through Thursday, April 1. Detour information is as follows:
    • Southbound Florida’s Turnpike/SR 91 traffic wishing to access Okeechobee Road/SR 70 (Exit 152) will be directed to exit at Port St. Lucie Boulevard (Exit 142), travel north on Bayshore Boulevard to Crosstown Parkway, travel west on Crosstown Parkway to I-95 northbound, travel north to access Okeechobee Road/SR 70 (Exit 129). For more information, please contact Fiorella Teodista at 954-663-0612.

INDIAN RIVER COUNTY

  1. 17th Street Bridge Project

Description: The 17th Street Bridge repair project from Indian River Boulevard to State Road A1A started May 4, 2020. Work on this project includes replacing all 35 light poles along the 17th Street Bridge and replacing concrete traffic railing along the median at the light pole locations. Associated work remaining includes repairing spalls in the concrete beams in spans 58 and 59 of the 62-span bridge which began October 26, 2020.

Cost/Completion: $1.1 million. Completion is expected in spring 2021.

Traffic Impact:

  • Eastbound and westbound traffic on the 17th Street Bridge is down to one lane in each direction around the clock through spring 2021 for bridge beam repairs. Currently, westbound traffic on 17th Street Bridge is diverted to the eastbound travel lane through Apr. 2021. For more information, please contact Community Outreach Specialist Kathleen Dempsey at 772-359-5118.

 

  1. State Road A1A Shoulder Widening and Resurfacing Project

Description: The State Road (SR) A1A shoulder widening and resurfacing project from north of Tides Road to south of Coco Plum Lane started June 22, 2020. The improvements on this project include: resurfacing SR A1A from just north of Tides Road to just south of Coco Plum Lane; widening SR A1A to provide 7-foot shoulders in each direction to accommodate new buffered bikes lanes; installing signalization improvements; upgrading pedestrian signal features at the SR A1A / John’s Island Drive and SR A1A / Wabasso Beach Road intersections with LED countdowns; constructing drainage improvements; installing new signs and pavement markings; reconstructing pedestrian ramps to meet current Americans with Disabilities Act (ADA) requirements; installing Rapid Flashing Beacons at two (2) beach access pedestrian crossing locations; and making sidewalk repairs at various locations throughout the project limits.

Cost/Completion: $6.7 million. Completion is expected in summer 2021.

Traffic Impact:

  • Along State Road A1A from north of 46th Place to south of Coco Plum Lane the speed limit has been permanently reduced from 50 MPH to 45 MPH. During construction, the speed limit is temporarily reduced from 45 MPH to 35 MPH.
  • The southbound and northbound bike lane is closed to facilitate shoulder widening construction. During this time, cyclists & motorists should share the road. For more information, please contact Community Outreach Specialist Kathleen Dempsey at 772-359-5118.

 

  1. State Road A1A from Gracewood Lane to Castaway Boulevard in Vero Beach

Traffic Impact:

  • The northbound shoulder of State Road A1A will be closed Monday through Friday from 9 a.m. to 4 p.m. for utility work. For more information, please contact Gus Sikaffy at 954-995-2760.

 

  1. State Road A1A from 23rd Street SE to Gracewood Lane in Vero Beach

Traffic Impact:

  • One lane in either direction State Road A1A will be shifted to the median turn lane Monday through Friday from 9 a.m. to 4 p.m. for utility work. For more information, please contact Gus Sikaffy at 954-995-2760.

 

  1. U.S. 1 at 53rd Street in Vero Beach

Traffic Impact:

  • One northbound lane of U.S. 1 will be closed Monday or Wednesday from 9 a.m. to 4 p.m. for utility work. For more information, please contact Maria Sacerio at 786-717-0896.

 

  1. U.S. 1 from North of 45th Street to South of 47th Street in Vero Beach

Traffic Impact:

  • One southbound lane of U.S. 1 will be closed Monday or Wednesday from 9 a.m. to 4 p.m. for utility work. For more information, please contact Maria Sacerio at 786-717-0896.

 

  1. State Road 60 from just West of 44th Avenue to 43rd Avenue in Vero Beach

Traffic Impact:

  • One eastbound lane of State Road 60 from just west of 44th Avenue to 43rd Avenue is closed around the clock through Apr. 2021 for drainage work.
  • One westbound lane of State Road 60 from just west of 44th Avenue to 43rd Avenue will be closed around the clock through Apr. 2021 for drainage work.
  • Full Closure: On Wednesday, Mar. 31, from 10 a.m. to 1 p.m. the intersection of State Road 60 and 43rdAvenue will undergo four five-minute full closures for utility work. For more information, please contact Matthew Kirkland at 813-716-6339.

 

  1. Indian River Boulevard from Merrill P. Barber Bridge to Royal Palm Boulevard in Vero Beach

Traffic Impact:

  • One southbound lane of Indian River Boulevard will be closed Monday through Friday from 9 a.m. to 4 p.m. through Apr. 23 for utility work. For more information, please contact Rosendo Raya at 305-248-9911.

 

  1. County Road 512 at the I-95 Overpass in Fellsmere

Traffic Impact:

  • Two westbound lanes of County Road 512 will be closed Sunday night from 9 p.m. to 6 a.m. for striping. For more information, please contact Ronnie Ward at 772-559-3009.

 

  1. State Road 60 at the I-95 Overpass in Vero Beach

Traffic Impact:

  • Advance Notice: One westbound lane of State Road 60 will be closed Tuesday night, Apr. 6 through Wednesday night, Apr. 7 from 9 p.m. to 5 a.m. for bridge work. For more information, please contact Diego Marentes at 772-215-9338.

 

###

Improve Safety, Enhance Mobility, Inspire Innovation

D4FDOT.com | @MyFDOT_SEFL | Facebook.com/MyFDOTSEFL